NEB recommends approval of Trans Mountain Expansion Project

In what will undoubtedly prove to be a controversial move with environmental and Indigenous groups, the National Energy Board (NEB) delivered its Reconsideration report to the Government of Canada on Friday of last week, with an overall recommendation that the Trans Mountain Expansion Project (Project) is in the Canadian public interest and should be approved.

The report is one of the factors that the Government will consider when making the final decision on whether or not the Project should proceed. The government has 90 days to make that decision under the NEB legislation but can extend that deadline.

The NEB will impose 156 conditions on the Project if it is approved, and has made 16 new recommendations to the Government of Canada. The recommendations relate to matters that fall outside of the NEB’s regulatory mandate, but within the authority of the Government of Canada.

The Reconsideration report concludes that Project-related marine shipping is likely to cause significant adverse environmental effects on the Southern resident killer whale and on Indigenous cultural use associated with the Southern resident killer whale. The NEB also found that greenhouse gas emissions from Project-related marine vessels would likely be significant.

While a credible worst-case spill from the Project or a Project-related marine vessel is thought unlikely, if it were to occur the environmental effects would be significant. While these effects weighed heavily in the NEB’s consideration of Project-related marine shipping, the NEB recommends that the Government of Canada find that they can be justified in the circumstances, in light of the benefits of the Project and measures to minimize the effects.

Those benefits include increased access to diverse markets for Canadian oil; jobs created across Canada; the development of capacity of local and Indigenous individuals, communities and businesses; direct spending on pipeline materials in Canada; and considerable revenues to various levels of government.

The Reconsideration specifically examined the impacts of Project-related marine shipping related to the application of the Canadian Environmental Assessment Act, 2012 and the Species at Risk Act (SARA) , as per the Government’s direction to the NEB in September 2018. The NEB has completed the Reconsideration within the 155 day timeline required by the Government of Canada.

If the Project is approved by the Government, the company must comply with 156 conditions, covering a wide range of matters including: emergency preparedness and response, protection of the environment; consultation with affected Indigenous communities; socio-economic matters; pipeline safety and integrity; commercial support for the Project prior to construction; and financial responsibility on the part of the company.

In addition, the NEB has made 16 recommendations to the Government of Canada related to Project-related marine shipping, including: cumulative effects management for the Salish Sea, measures to offset increased underwater noise and increased strike risk posted to SARA-listed marine mammal and fish species, marine oil spill response, marine shipping and small vessel safety, reduction of GHG emissions from marine vessels, and the Indigenous Advisory and Monitoring Committee for the Project.

https://www.neb-one.gc.ca/bts/nws/nr/2019/nr04-eng.html

____________________________________________________________

Manning Environmental Law is a Canadian law firm based in Toronto, Ontario. Our practice is focussed on environmental law, energy law and aboriginal law. 

Paul Manning is a certified specialist in environmental law. He has been named as one of the World’s Leading Environmental Lawyers and one of the World’s Leading Climate Change Lawyers by Who’s Who Legal.

As always, these posts  are provided only as a general guide and are not legal advice. If you do have any issue that requires legal advice please get in touch. Our contact details can be found here

This entry was posted in Energy, Energy Regulation, Environment, Environmental, Environmental Approvals, federal environmental regulation, Uncategorized, Wildlife and Endangered Species and tagged , , , , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s